Cottonwood Drive Construction Update - October 31, 2018

Here is the latest from the Ottawa County Road Commission on the Cottonwood Drive project:


 

Contractors continue to make headway on the easterly side of Cottonwood Drive following paving of base and leveling courses of asphalt on the westerly side of the road last week.

With the old road surface removed, contractors continue to install storm water catch basins along the eastern side of Cottonwood Drive. The goal is to complete the installation of the catch basins by the end of this week.

If crews are able to get the storm water catch basins installed this week, work will begin over the next two weeks to install new concrete curb and gutter, and segments of sidewalk on the east side of Cottonwood.

On the west side of Cottonwood, work continues on concrete driveway and sidewalk installation. Watch for lane closures as crews pour new concrete surfaces.

Over the next two weeks, also anticipate crews to come out and complete the leveling course of asphalt in the intersections along the westerly side of Cottonwood.

Please be reminded that Cottonwood Drive remains closed to thru traffic for the duration of the reconstruction project. The detour route for the project is Baldwin Street to 20th Avenue to Bauer Road to 24th Avenue to Fillmore Street.