Cottonwood Drive Construction Update October 3, 2018

COTTONWOOD DRIVE UPDATE: OCT 3, 2018

Construction crews have been busy out on Cottonwood Drive the past several days, starting back up in full force on the project this past Monday.

Here’s the latest project update:

  • The 84-inch drain pipe being worked on at Village Lane is anticipated to be completed by the end of the day today (Oct. 3), weather permitting.
  • Additional concrete curb and gutter installations are expected to begin the week of Monday, Oct. 8.
  • A lane closure on the right lane of westbound Baldwin Street as you approach Cottonwood will begin Monday, Oct. 8, as crews work on curb and gutter, and drainage installation on the northwest corner of the Cottonwood Drive/Baldwin Street intersection. The lane closure is expected to last through Friday, Oct. 12.
  • Contractors will be grading the western side of Cottonwood, with a tentative goal of paving a base course of asphalt on that side of the road the week of Oct. 15.
  • Contractors continue to work on water main and water service tie-ins along Cottonwood ahead of anticipated paving on the west side of the road.

As a reminder, even with the culvert work at Village Lane anticipated to be complete this week, Cottonwood Drive is still closed to thru traffic. Please follow all posted detour routes. The detour route for the project is Baldwin Street to 20th Avenue to Bauer Road to 24th Avenue to Fillmore Street.